5月25日,长庆分公司苏南—C2集气站两套压缩机机组成功吊装就位,标志着苏南-C2集气站建设进入了一个新的阶段,对于提高集气站的生产效率和保障供气稳定具有重要意义。

据悉,本次苏南-C2集气站扩建区共吊装了2套压缩机机组,两套机组均由主机、电机、一级分离器、空冷器等组成,主机重量分别为55吨和60吨,机组总重达118.6吨和140.6吨,整个吊装作业采用一台50吨和一台500吨吊车配合完成。


为确保整个吊装作业的安全顺利进行,苏南项目部提前编制压缩机组吊装施工技术方案,对现场进行了全面细致的安全检查,并组织了专业的吊装团队进行操作。在吊装过程中,工作人员严格按照操作规程进行,确保了吊装过程的平稳和准确,历时近1天完成本次吊装作业。

此次2套压缩机机组的成功吊装就位,是长庆分公司苏南—C2集气站建设中的一次重要突破,为集气站的早日投产奠定了坚实基础,也为苏南地区的能源供应提供保障。
The weather is cool and it's a fine autumn; September is only suitable for traveling.
Night Battle on the Great River | Water levels are rising, pipelines are extending
The summer colors fade in the clouds and sky; the pipes welcome the sounds of autumn.
The hot connection has been successfully completed, and the well cluster is about to be put into production.
Practical drills to prevent heatstroke, building a solid safety line for summer
An oil worker who has taken off the military uniform is still a soldier at heart.
Sweat-soaked workwear is the simplest answer to this summer.
The temperature is 40°C, the welding sparks are 1500°C, how "fiery" is the summer for workers?
July 1st | The direction of light is also the path we have walked.
EACOP Uganda Section: Over the Great River, the pipeline is crossing.